CADOGAN

Construction Update November 2020

Works continue on site to fit out the 30 bedrooms / suites for the new hotel. Externally the new underpins and foundations along Sloane Gardens, in the position of the now removed crane base are nearing completion, with these works to be finished in the coming month.

Also externally, work to replace the flat roof to the rear of 3 Sloane Gardens will commence in November.  Internally, the break through at basement level from 1 to 3 Sloane Gardens continues, along with the structural works to form the new toilets in the basement, to serve the hotel bar and restaurant.

Cadogan have provided additional space for the construction management team in Lower Sloane Street, allowing the welfare provision at 11 Sloane Gardens to be expanded for the operatives, to accord with Covid-19 distancing recommendations.

Go back
Next